WFM Re-optimizing Period – Calendar or Trading Days
2 replies
AC1962
7 years ago #116115
Hi Marc
Please can you confirm: When using SQ 3.8.1 WFM tool, should the recommended re-optimizing periods reported as “every ‘x’ days on history ‘y’ days” be read as ‘calendar days’ [365/yr] or ‘trading days’ [~260/yr]? See attached screenshot.
Thanks
AC1962
tomas262
7 years ago #140727
Hello,
it is meant to be trading days actually since we have the data only available for the days where the market is being traded (open)
AC1962
7 years ago #140731
Great, thanks Tomas!
I previously conservatively assumed calendar days. So changing to trading days (which on reflection is more logical) now gives more time before the need for strategy re-optimization.
Thanks again
AC1962